Wednesday, June 30, 2010

Week 3 Day 3

Big day today: Cabinets delivered, Tile laid, Priming started, Trim finished, Mantle Wired, Drywall Completed (probably on the last one). Everything is being completed in preparation for a Friday install of the cabinets. This should take two days so Friday/Saturday or Friday/Monday (he doesn't want to force anyone to work on Saturday over the holiday weekend but thinks Arthur may volunteer anyway).

Next looming decision for us to make is the stone type for the counters